Maine Elementary School Design Milestones

April 2024 — 95% Design Complete
Design work is close to final for Maine ES site work (fencing and fire department access), secure entrance, front office, and ADA upgrades. Non-ADA casework has been removed and additional accessibility features are in the works.

Click here for more information on the 95% design updates presented to the School Board this month.

February 2024 — 50% Design Complete
As Maine’s Design progresses to the halfway mark, plans for the secure entrance, office, and student services area remodels are coming together with floor plans (at left).

Work continues on refining the plans and adjusting the scope for existing conditions. Some of the focus areas at this site include:

  • Updates to Fire Department access and fencing

  • Entrance security enhancements

  • Student Services remodeling

  • ADA upgrades to include cubbies, vertical grab bars, door hardware, and electric water cooler