June 2023 Construction Update - South Mountain

 

PROGRESS TO DATE

  • Exterior work continues on roofing, concrete, insulation, and brick veneer

  • Interior work continues including painting, ceilings, masonry and tiling work

  • Front office remodeling is about 50% complete

  • Work on fire alarm upgrades continues


May 2023 Construction Update - South Mountain

 

PROGRESS TO DATE

  • 95% of EPDM roofing in  Area B is complete

  • Completed slab preparation and exterior insulation for Area B

  • 75% of HVAC rough in for Area B is complete

  • Completed construction of bearing masonry in Area C

  • Installed bar joist and metal deck in Area C

  • 50% of EPDM roofing is complete in Area C

  • Completed plumbing tie in from existing building

  • 75% of fire alarm upgrades in existing building are complete


Design Work 95% Complete at South Mountain

Exterior Rendering

As South Mountain’s Design process nears completion, plans are coming together nicely. Interior finishes for windows, doors and flooring have been selected to match existing finishes.

Areas of work at South Mountain include:

  • two classroom additions to create six new rooms, including two for kindergarten

  • upgrading front entry and ADA access (doors, cubbies)

  • LED lighting,

  • air handling units

  • fire and safety systems

  • plumbing

Click here to see design updates.


Design Work is 50% Complete at South Mountain

South Mountain Design is halfway through the process and, after weeks of design and user group meetings, plans are coming together nicely. A notable development was the decision to relocate the existing walking path and fire lane. Click here to see design plans to date.