June 2024 Construction Update

Work at West High School is progressing quickly this summer. Progress to date at this building is focused on these three areas:

  • Front Entrance and Auditorium Addition – Roof deck and interior walls are installed, roofing and brick are over 90% finished, and work on interior walls continues (paint, drywall)

  • Fitness Addition – Existing fitness center was demolished and work on footings and foundations work has begun.

  • Locker Rooms and Interior Renovations – Phase 1 of the locker room renovations is complete and renovations planned for the first and third floor are underway.

For a glimpse of the construction work underway this Summer, click here for updates presented to the School Board in June 2024.

Design for Multi-Purpose Field at West High School Approved for Bidding

On May 13, the Board of Education reviewed and approved the final design and budget for the Multi-Purpose Field Project at West High School which means the project is ready for bidding. Some of the notable updates approved include:

  • new field lighting for football, track and field events

  • new synthetic turf on existing field for multi-purpose use(Lacrosse, Soccer, Football)

The attached design update highlights field and lighting layouts from the 95% phase. Design work is concluded and work is expected to begin later this Summer.

Click here for details on design updates presented to the School Board in March 2024.

Design for Multi-Purpose Field at West High School Reaches 50% Milestone

Design work for the multi-purpose field at West High School is 50% complete as the team considers needs to create a space that supports Lacrosse, Soccer, and Football.

To date the user group meetings have focused on athletic field lighting and turf, and the work includes:

  • new soccer goals, posts, and pads

  • new areas of concrete

  • surface area drainage

The attached design update highlights field and lighting layouts at the 50% phase. Design work is expected to conclude this Spring and work is expected to begin later this Summer.

Click here for details on design updates presented to the School Board in March 2024.

West High School Design Work is 95% Complete

Design work at West High School has impacted all three floors and is now 95% complete, with renderings and floor plans close to final. The Design Team continued its focus on creating future-ready, functional and inspirational spaces for students and staff.

To date there have been 15 user group meetings which included the principal, maintenance staff, teachers, and staff in front office, Theater, Special Education, Physical Education, Athletics, Music, Student Services, ​Library, Foods, Kitchen​, and IT areas.

The attached design update highlights notable progress to date on site work, building additions, and renovations.

Click here for details on design updates presented to the School Board in June 2023.

Design Work is 50% Complete at West High School

PRELIMINARY RENDERING

As West’s Design progresses to the halfway mark, and after weeks of design and user group meetings, plans are coming together with preliminary renderings (at right) and floor plans. Work continues on refining the plans, and areas of focus at this site include:

  • front office, athletic, and theatre additions

  • student services, special education, and music wing renovations

  • robotics, foods, and FCE classroom remodels

  • commons, kitchen, community room, and PE remodels

Click here to see the design update presented to the School Board.