June 2023 Construction Update - Stettin Elementary

 

PROGRESS TO DATE

  • Majority of interior doors and windows are installed

  • 95% of interior painting is complete

  • 95% of HVAC system for addition is installed

  • 85% of casework and flooring are installed in classrooms and corridors

  • 85% of electrical system for addition is complete

  • Plumbing and bathroom floor and wall tile complete


May 2023 Construction Update - Stettin Elementary

 

PROGRESS TO DATE

  • Installed interior concrete slabs

  • 95% of interior non-load bearing masonry walls are complete

  • 65% of HVAC rough in for addition is complete

  • 70% of electrical rough in for addition complete

  • 90% of plumbing rough in   is complete

  • 75% of exterior veneer is complete


Design Work is 95% Complete at Stettin Elementary

 

As Stettin’s Design progresses to the 95% complete, plans are coming together nicely. Interior finishes for windows, doors and flooring have been selected to match existing finishes.

Areas of work at Stettin include LED lighting, air handling units, fire and safety systems, plumbing, casework and cubbies.

Click here to see 95% design updates.


Design Work is 50% Complete at Stettin Elementary

As Stettin’s Design progresses to the halfway mark in the process, and after weeks of design and user group meetings, plans are coming together nicely. While the floor plan for the classroom addition and secure entry remained the same, the playground was relocated. Click here to see design updates.